Today (17/1) the new Wärtsilä machine arrived in the new machine hall in Amfilochia. The installation and test run started immediately and is expected to be completed in seven to ten days.
During the installation, we disconnect the existing machines that have been producing electricity since they were started on December 13.
Machine shop in Amfilochia
Our new supplier has started delivering the panels. These are necessary to protect the machine and critical equipment from both weather and other damage, and to ensure the legally required soundproofing. Once all the panels have arrived, the machine is moved up to Amfilochia and the new machine shop is finally assembled.
We have now received the final delivery of the panels and they are being transported up to Amfilochia for assembly.
The work of installing the panels on the machine hall is now in full swing.
Restart in Amfilochia
Restart in Amfilochia
Zazz Energy has restarted the machines in Amfilochia and they are fully producing electricity. Turn up the volume…